Pimpri-Chinchwad: Fresh findings in the investigation into the Moshi waste-to-energy plant collapse have raised serious questions over possible irregularities in the construction of the administrative building that partially collapsed earlier this week.
The probe has found that the Pimpri Chinchwad Municipal Corporation (PCMC) had issued a completion certificate only for the ground floor of the building. Officials have now said there is no record showing that permission was granted for the construction of the first and second floors, even though both floors were reportedly in use as a canteen and conference hall at the time of the accident.
Visit rouesnews.click for more information.
WATCH: 60 hours since the Moshi garbage depot disaster. 23 people were trapped. 14 were rescued in the first 24 hours. 1 dead body has been recovered. 8 are still missing. Another demolition excavator has now been deployed along with others. The rescue continues... #Moshi #Pune pic.twitter.com/UhtBQbxJUq
— Varad Bhatkhande | Journalist (@VaradBhatkhande) July 10, 2026
More than 45 hours after the Moshi waste plant collapse, the rescue operation is still on. One person has lost their life, while eight remain trapped beneath the debris. Every passing hour makes the operation tougher. Hoping the teams on the ground pull off more miracles. #Pune pic.twitter.com/gVxWymM24u
— Varad Bhatkhande | Journalist (@VaradBhatkhande) July 10, 2026
The collapse triggered a massive rescue operation that continued for nearly 65 hours. One worker died in the incident, while rescue teams continued efforts to trace the remaining missing workers.
Documents examined during the investigation show that the PCMC Building Department issued the completion certificate for the ground floor on 27th July 2023. However, civic officials said no approval was sought or granted for the upper two floors.
City Engineer Manoj Sethiya confirmed that the civic body has no documents showing permission for the first and second floors. The disclosure has raised questions about how the additional floors were constructed and later occupied.
PCMC Waste-To-Energy Building Collapse: Rescue Operation Underway In Moshi As Voices Heard From Beneath Debris | WATCH VIDEOSThe approval process has also come under scrutiny. Records indicate that the PCMC Environment Department submitted a proposal for revised construction on July 26, 2023. A completion certificate for the ground floor was issued the very next day. Allegations have now surfaced that the certificate was granted without a physical inspection of the building.
Investigators are now trying to determine who allowed the upper floors to be constructed and occupied despite the absence of official approval. They are also examining whether there were lapses by civic officials, the contractor or others associated with the project.
The tragedy has intensified demands for accountability. Questions are being raised over whether responsibility lies with the then executive engineer of the environment department, the contractor or other officials involved in the project.
Pune Breaking: Pimpri-Chinchwad Building Collapses; 15–20 Labourers Feared Trapped At PCMC Waste-To-Energy Project Site | WATCHMeanwhile, family members of the affected workers met PCMC Additional Commissioner Kuldeep Jangam and demanded strict action against those responsible. They also sought assurances about compensation and the future of the injured workers and their families.
The relatives expressed concern over the financial security of the victims, including Akshay Gaikwad, who had recently married and has young children. They urged the civic administration to fix responsibility at the earliest and ensure action against those found guilty.